Re: Elapsed Days in Predecessor Field
Please allow for this , have submitted over and over again. =32fs+30ed3 · -
Kanban cards take lowest level
Need to be able to set Kanban to the activity level rather than deliverable/subdeliverable level when managing projects. We have a workwround that requires a checkbox or we will develop a complex for…1 · -
Automatic WBS Numbering
We have a work around but it takes multiple helper columns and complex formulas. You need WBS numbering 1 1.1 1.1.121 · -
Elapsed Time in Predecessors
We have a combination of production activities that go round the clock and people related activities that don't use weekends. IN Microsoft Project, I am either to get around this issue by either sett…2 · -
Re: Elapsed Time in Predecessors
Smart sheet does not seem to allow for ELAPSED TIME in predecessors such as 3FS+e4d. IT does allow for it in durations. This creates difficulties in creating timelines when production activities (7 d…4 ·